First thing I did was downloaded the latest PRINCE2 2009 Process Model diagram which is available in PDF on the PRINCE2 website.
Next I loaded up Microsoft Project 2010 and entered the high level task I am going to use which in this case is the ‘Starting up a project’ stage.
Next I want to add a subtask which will be the start of my list of activities assigned to the ‘Starting up a project’ task.
To make this task a subtask of the line above click on the
icon on the ribbon. I then added the other activities in the same way.
Now I have added my activities as subtasks I can now start to assign durations to them. These can obviously be changed but for now the typical rule is whatever you estimate then 100%.
You can see that it has underlined the Finish date of the task because I have subtasks that require more time. Some of the subtasks are done in a specific order so I am now going to add the number of the preceding task in the Predecessors cell which will move the tasks around on the Gantt chart.
I could also add resources and so on but I will leave it there for a simple introduction to adding tasks and subtasks to a project file in Project 2010. You will see that it has moved the entries around but the Finish date of the original task is still the same as before. You could enter in a new date or click on the task and click on the Auto Schedule button on the ribbon or use Ctrl + Shift + A on the keyboard. Now we can see that our project stage is due to end on 24/12/2009.
I hope that interests somebody. Entering new tasks and subtasks in Project 2010 seems a little more intuitive than with previous versions but only time will tell.
March 23rd, 2011 at 11:46 am
I am just starting out on Ms Project and this helped a lot. Excellent explanation of the concepts. Thanks a lot for the effort to publish the article.
April 7th, 2011 at 2:44 am
Very well explained!
April 28th, 2011 at 3:49 pm
Great, helped a lot, thanks
November 15th, 2011 at 2:53 pm
Very useful article for MS Project beginners.
This short essentials overview helped me a lot.
December 8th, 2011 at 2:37 pm
I’d like to be able to add a subtask through .Net and C#
Would you have a snippet?
I’m currently able to add tasks via C# but not subtasks to an existing task.
December 12th, 2011 at 9:36 am
I don’t have a snippet to hand sorry but I can’t imagine it would be hard. Look in the tasks collection for the task you require then add a subtask to that task sounds like the logical route?
Sorry I can’t help you more.
March 15th, 2012 at 12:18 pm
Worth a million words..helped tremendously!!!
August 8th, 2012 at 9:03 am
Great job, big help for beginners….
August 16th, 2012 at 4:06 am
Very helpful stuff and detailed one..Thank you!
December 5th, 2012 at 7:02 am
This very usefull thanks for this post….
April 5th, 2013 at 1:14 pm
Well explained. Thank you
May 8th, 2013 at 9:58 am
Is all clear. Thanks man!